§ Mr. AdleyTo ask the Secretary of State for Transport how long it will take to intall safety fencing along the A31 trunk road at West Moors between Pinehurst roundabout and Boundary lane; and what are the reasons for the time taken.
§ Mr. AtkinsThe work will take about three months. This is because of the need for carriageway works to enable the central reserve to be widened to accommodate the 850m long safety fence without interfering with statutory undertakers' services.