§ Mr. MuddTo ask the Secretary of State for Transport if he will list all trunk road schemes for which public inquiries have been completed but no ministerial decision has yet been made on the inquiry inspector's recommendation, giving the date on which the inquiry was closed; and, where the report has been submitted by the inspector, the date on which the report was presented to the Secretary of State for decision.
§ Mr. Atkins[holding answer 22 June 1990]: The following schemes in the national programme for England are awaiting a decision following a public inquiry:
21W
Public inquiry finished Inspector's report received A629 Skipton-Kildwick improvement June 1990 Awaited A650 Airedale route (Crossflatts-Cottingley Bar) March 1990 Awaited