HC Deb 21 June 1990 vol 174 c657W
Mr. Salmond

To ask the Secretary of State for Energy (1) what are the estimated quantities of low and intermediate level waste arising from the decommissioning of the thermal oxide reprocessing plant at Sellafield;

(2) what is his estimate of the cost of decommissioning the thermal oxide reprocessing plant at Sellafield.

(3) how the costs of decommissioning the thermal oxide reprocessing plant at Sellafield will be met.

Mr. Baldry

The work of decommissioning plant operated by British Nuclear Fuels plc and estimates of the costs of that work are matters for the company.