HC Deb 05 July 1990 vol 175 c641W
Mr. Bermingham

To ask the Secretary of State for the Home Department what has been the cost to date of the prison building programme; what is the estimated cost of the remaining planned institutions; and if he will make a statement.

Mr. Waddington

The total capital cost of the 8 prisons already constructed is £223 million, at outturn prices. The costs of the remaining 16 prisons in the current prison building programme are estimated at £1,132 million, also at outturn prices, of which £336 million had been spent up to the end of March 1990.