HC Deb 13 December 1990 vol 182 c485W
Mr. Morgan

To ask the Secretary of State for Energy (1) what estimate he has made of the effects of the reported delays in the completion of the secondary safety computer system for the Sizewell B pressurised water reactor nuclear power station on(a) the non-fossil fuel obligation and (b) the external financing limit of Nuclear Electric;

(2) what discussions he has had with the chairman of Nuclear Electric concerning delays in completing the software for the operational secondary safety systems at the Sizewell B nuclear power station;

(3) what information he has received from the nuclear installations inspectorate about delays in the development of the operational secondary safety computer system for the Sizewell B nuclear power station.

Mr. Heathcoat-Amory

The proposed protection system for Sizewell B consists of a computer-based primary protection system and a non-computer based secondary system. The Health and Safety Executive's nuclear installations inspectorate is satisfied with the progress being made in the development of both systems.

The construction of Sizewell B power station is a matter for Nuclear Electric plc. The company has informed me that the construction of the station is proceeding ahead of schedule.