§ Mr. MarlowTo ask the Secretary of State for Transport when he expects the contract for junction 15A on the M1 to be let; and when he anticipates it being completed.
§ Mr. AtkinsThe construction of the new junction 15A on the M1 motorway in Northamptonshire is part of the contract for the A43 Blisworth and Milton Malsor bypass.
A £15 million contract for construction of the bypass has been awarded to Calliford Engineering and work started on site on 18 April. Construction is expected to take about two years.