HC Deb 03 April 1990 vol 170 c587W
14. Mr. Norman Hogg

To ask the Secretary of State for Defence how many weapons development procurement projects have exceeded their original estimates by more than 10 per cent.; and what is the total amount of overspend involved.

81. Mr. Eastham

To ask the Secretary of State for Defence how many weapons development procurement projects have exceeded their original estimates by more than 10 per cent.; and what is the total amount of overspend involved.

84. Mr. Graham

To ask the Secretary of State for Defence how many weapons development procurement projects have exceeded their original estimates by more than 10 per cent.; and what is the total amount of overspend involved.

100. Mr. Fatchett

To ask the Secretary of State for Defence how many weapons development procurement projects have exceeded their original estimates by more than 10 per cent.; and what is the total amount of overspend involved.

Mr. Alan Clark

Three major weapons projects currently in development or production have, in real terms, exceeded their original estimate by more than 10 per cent.; the total amount involved, in current prices, is £383 million.