HC Deb 03 April 1990 vol 170 c514W
Mr. Morgan

To ask the Secretary of State for Energy what is the latest estimate of the date of Sizewell B's(a) completion, (b) commissioning and (c) run-up to full power.

Mr. Baldry

The timetable for completion of Sizewell B is a matter for Nuclear Electric plc. The CEGB indicated in its last annual report and accounts that it aimed to achieve full commercial load in May 1994, six months after the start of fuel loading.