§ Mr. PageTo ask the Secretary of State for Transport if he will estimate the likely final cost of the completed improvement works to the existing Severn crossing.
§ Mr. AtkinsThe final cost of stengthening and resurfacing the Severn crossing is estimated at £70 million.
§ Mr. PageTo ask the Secretary of State for Transport what is the progress to date and likely completion date of improvement and strengthening work to the existing Severn crossing.
§ Mr. AtkinsStrengthening work on the Severn crossing will be completed during the course of 1990. Resurfacing of the crossing is due to be completed by early 1991.