HC Deb 19 October 1989 vol 158 c256W
Mr. Kirkwood

To ask the Secretary of State for Defence if he will list in theOfficial Report those weapons and systems projects in the last five years for each of the three services which have been cancelled or otherwise aborted prior to being brought into service, showing the amount of development money lost prior to cancellation and as a proportion of the total budgeted cost of the original project.

Mr. Alan Clark

Major weapons systems projects which had entered full development and which were subsequently cancelled, in the last five financial years, prior to being brought into service are as follows:

(a) Project (b) Service (c) Expenditure at Cancellation (£ million) (d) (c) as a percentage of estimated Project Total
CACS 4 RN 139 14
SP70 Army 88 35
Nimrod AEW RAF 660 50
1 Part of the development cost of CACS 4, amounting to £11 million, was previously commercially sensitive.