HC Deb 08 November 1989 vol 159 c641W
Mr. Higgins

To ask the Secretary of State for Transport if he will make it his policy that detailed design work will be prepared for both his Department's preferred route for the A27 in the Worthing area and a real bypass in advance of the public inquiry.

Mr. Atkins

In the special circumstances of the A27 Worthing-Lancing scheme, we have undertaken to carry out full traffic, economic and environmental assessments of the alternative "blue" bypass routes that have been put forward as well as of our preferred "green" route announced in July. This will ensure an adequate basis for all the issues to be thoroughly debated at a public inquiry.

We could not justify carrying out detailed design work on routes other than the one to be published in draft orders unless, following an inquiry, we were persuaded that such an alternative route should be adopted.

Forward to