§ Mr. McFallTo ask the Secretary of State for the Environment what length of delays will be experienced in the shiplift project at Faslane as a result of the construction difficulties being experienced by the contractor.
§ Mr. ChopeThe delay to the shiplift construction programme is about six months but this will be contained within the float from the overall works programme.
497W
§ Mr. McFallTo ask the Secretary of State for the Environment what will the extra costs involved as a result of the delay in construction of the shiplift project at Faslane; and who will bear these costs.