§ Mr. LivseyTo ask the Secretary of State for Wales when he will be able to publish the final line of route of(a) the Talgarth and (b) the Crickhowell bypass.
§ Mr. Wyn RobertsNot for some time yet.
Public consultation on alternative options for a bypass of Talgarth will be undertaken towards the end of the year and a fee competition for the appointment of consultants to undertake a bypass feasibility study for Crickhowell will be held shortly.
§ Mr. LivseyTo ask the Secretary of State for Wales during which year he expects work to commence on(a) the Talgarth and (b) the Crickhowell bypass.
§ Mr. Wyn Roberts"Roads in Wales 1989—Progress and Plans for the 1990's" shows Talgarth bypass for possible start in the medium term period April 1991 to March 1994 and Crickhowell bypass as a long-term scheme unlikely to start before 1994–95. It is not possible to be more precise.