HC Deb 17 May 1989 vol 153 cc226-7W
Mr. Robin Cook

To ask the Secretary of State for Scotland if he will give detail of each capital project costing more than £1 million(a) actually under construction and (b) at the proposal or planning stage; if he will give the estimated date of completion for each project; and if he will break this list down by each region.

Mr. Michael Forsyth

There are no health regions but the information for Scotland is as follows:

Estimated date of Completion
Projects Under Construction
Pollok Health Centre, Glasgow Spring 1989
Castlemilk Health Centre, Glasgow Spring 1989
Raigmore (Control of Infection Unit and on-call accommodation), Inverness May 1989
Balfour Hospital, Kirkwall July 1989
Gilbert Bain Hospital (Phase I), Lerwick August 1989
Ravenscraig Phase IIIA, Greenock (Alcohol and Rehabilitation Unit) December 1989
Dumfries and Galloway Services for the mentally handicapped 11989
City Hospital, 2nd 60 bed unit, Aberdeen May 1990
Seafield Hospital, Ayr December 1990
West Lothian District General Hospital, Livingston
a. Phase II 1991
b. Residences February 1990
Royal Cornhill Phase I, Aberdeen Spring 1991
Royal Infirmary, Perth April 1991
Acute Hospital, Ayr July 1991
Maternity Hospital, Bellshill 1992
Hairmyres Hospital, East Kilbride 1992
Udston Hospital, Hamilton 1992
Western Isles Hospital, Stornoway 1993
Schemes Completed but under Commissioning
Royal Infirmary Phase I, Stirling Due to open October 1989
West Lothian District General Hospital Phase I, Livingston Due to open October 1989
Projects at Proposal or Planning Stage
Whitefield Road Phase II, Dunfermline 1990
Edinburgh Dental Hospital 1991
Oban Hospital 1991–92
Campbeltown Hospital 1992–93
Bo'ness Hospital 1993
Lochgreen Hospital, Falkirk 1993
Royal Scottish National Hospital, Larbert 1993
Ayrshire Central Laundry not known
Rutherglen Geriatric Services not known
Leverndale Support Services not known
1 This is a phased development on a number of sites, other stages will follow.

Mr. Robin Cook

To ask the Secretary of State for Scotland if he will give, for each region, details of proposed capital developments costing more than £1 million which have been cancelled for each year since 1979.

Mr. Michael Forsyth

No hospital project has been cancelled by my right hon. and learned Friend or his predecessor since 1979.