§ Mrs. ClwydTo ask the Secretary of State for Energy what are the expected total costs of the Sellafield thermal oxide reprocessing plant once completed; and what is the estimated running costs of its first year.
§ Mr. Michael SpicerThe expected total cost of the thermal oxide reprocessing plant at Sellafield is some £1,800 million. It is too early to estimate precisely the running costs for its first year.