HC Deb 13 February 1989 vol 147 c97W
46. Mr. Franks

To ask the Secretary of State for Transport how many objections have been received

Scheme Works cost £ million
A361 North Devon link road stage 1 (M5 Sampford Peverell to Tiverton) 17.3 Completed March 1984
A361 North Devon link road stage 2A (Tiverton to Newtown) 27.6 Completed November 1988
A361 North Devon link road stage 2B (Newtown to Barnstaple) 25.3 Started October 1987
A39 Barnstaple bypass 20.5 Started August 1987
A39 Bideford bypass 18.3 Completed May 1987

The cost of connecting roads are included.