HC Deb 08 February 1989 vol 146 cc694-5W
Dr. Thomas

To ask the Secretary of State for Energy (1) when he plans to announce the opening date and name of the inspector for the Sizewell C public inquiry into the Central Electricity Generating Board planning application for a new pressurised water reactor at its Sizewell nuclear site;

(2) if it will be the responsibility of National Power to cover the costs of the Sizewell C planning inquiry, including the fee for the inspector and the publication cost of daily transcripts and support documentation.

Mr. Michael Spicer

The CEGB announced on 31 January its intention to submit an application to my right hon. Friend for his consent to construct a pressurised water reactor nuclear power station at Sizewell in Suffolk. Before the application has been made and advertised and the response to it is known, it is too early to speculate about a public inquiry.