§ Mr. ThurnhamTo ask the Secretary of State for Transport if he will list the road building work contracts in the north-west during 1988–89 scheduled to cost over £1 million.
§ Mr. Peter BottomleyFollowing is the table:
Scheme Total cost excluding land M63 (junctions 1–3) 21.0 M63 (junctions 3–5) 21.7 M63 Portwood-Brinnington 45.5 M66 Brinnington-Denton M62 widening (junctions 21–22) 10.00 A565 Derby Road improvement 2.1 A483 Gresford-Pulford bypass 14.6 1 English section only. In addition work has been carried out on five major motorway maintenance contracts with a value of over? 1 million. Contracts on local authority roads are not included.