HC Deb 06 February 1989 vol 146 cc534-5W
Mr. Thurnham

To ask the Secretary of State for Transport if he will list the road building work contracts in the north-west during 1988–89 scheduled to cost over £1 million.

Mr. Peter Bottomley

Following is the table:

Scheme Total cost excluding land
M63 (junctions 1–3) 21.0
M63 (junctions 3–5) 21.7
M63 Portwood-Brinnington 45.5
M66 Brinnington-Denton
M62 widening (junctions 21–22) 10.00
A565 Derby Road improvement 2.1
A483 Gresford-Pulford bypass 14.6
1 English section only.

In addition work has been carried out on five major motorway maintenance contracts with a value of over? 1 million. Contracts on local authority roads are not included.