HC Deb 06 May 1988 vol 132 c647W
Dr. Thomas

To ask the Secretary of State for Scotland what have been the total investment costs for each of the South of Scotland Electricity Board nuclear power plants in(a) historic costs and (b) current costs to date.

Mr. Lang

The South of Scotland Electricity Board has provided the following information based on its accounts for the year ending 31 March 1987:

£ million
Hunterston A Hunterston B Torness
Historic costs 88.6 299.0 1,704.7
Current costs 623.0 917.9 2,046.3

Dr. Thomas

To ask the Secretary of State for Scotland what benefits he expects to accrue to the Scottish economy, and in particular Caithness, from the maintenance and expansion of the Nuclear Power Development Establishment at Dounreay.

Mr. Lang

Consideration of the future of the fast reactor research programme, a major part of which is based at Dounreay, is the responsibility of my right hon. Friend the Secretary of State for Energy. I recognise that activities at the Dounreay establishment are of substantial economic benefit to the local community in Caithness.

Back to
Forward to