§ Mr. Gordon BrownTo ask the Secretary of State for Defence when he expects the refitting of HMS Valiant to be completed.
§ Mr. SainsburyThe refitting of HMS Valiant is currently expected to be completed in the latter half of this year.
§ Mr. Gordon BrownTo ask the Secretary of State for Defence if he will make a statement on the incident involving the repair of pipes leading from the nuclear reactor in HMS Valiant.
§ Mr. SainsburyI am glad to say that there has been no incident affecting nuclear safety on board HMS Valiant during her refit.
686W
§ Mr. Gordon BrownTo ask the Secretary of State for Defence if he has renegotiated the price for the refitting of HMS Valiant.
§ Mr. SainsburyBecause the refit of HMS Valiant commenced before the introduction of commercial management, it was not practicable to negotiate a fixed price contract at the outset. It has since been agreed that labour costs will be covered by incentive arrangements. Other elements, for example, materials and sub-contract costs, will be priced on the basis of actual ascertained costs. Any extra work under the contract will be covered by these arrangements.