HC Deb 03 March 1988 vol 128 c647W
Mr. Stern

To ask the Secretary of State for Energy when he expects the first flue gas desulphurisation plant to come into operation.

Mr. Michael Spicer

The CEGB envisages that the first stage of FGD plant planned for the Drax power station will be operational by 1993.

Back to
Forward to