To ask the Secretary of State for Social Services if he will list in chronological order by start date the hospital schemes costing over £5 million, started since 1979, giving in each case(a) the date of start on site, (b) the actual or intended completion date, (c) the number of beds involved, (d) the number of operating theatres involved, (e) the total cost and (f) the regional and district health authority; and if he will also give the number of such schemes costing over £1 million during the same period.

Mrs. Currie

The information requested on the 83 health building schemes over £5 million which have started construction since 1979 is provided in the table. In addition, 338 schemes each costing between £1 million and £5 million, were started in this period.

Project/Scheme Contract dates Region District
Construction cost (£) Start Complete Actual or estimated completion Number of beds Number of theatres
West Somerset (Musgrove Park) DGH. Phase 1 649,956,2.00 8 November 1982 8 November 1985 10 October 1986 150 2 South-Western Somerset
St. Mary's W2. Phase 1B 20,521,915.00 22 November 1982 22 February 1987 15 April 1987 338 8 North West Thames Parkside
Royal Hampshire County Winchester, Phase 4 (Nucleus) 10,442,215.00 8 December 1982 6 December 1985 16 May 1986 278 4 Wessex Winchester
Northern General. Phase 1C 6, 114,955.00 31 January 1983 28 October 1985 3 May 1985 236 Trent Sheffield
Blood Products Manufacturing Unit. Elstree 13,845,000.00 1 May 1983 1 November 1985 30 June 1988 Special Health Authority
Great Ormond Street Remedial Works 7,650,000.00 15 August 1983 15 August 1985 1 September 1987 6 Special Health Authority
Royal South Hampshire Southampton, Phase 3 11,044,487.00 17 October 1983 17 October 1986 15 December 1986 20 Wessex Southampton
Scarborough DGH, Phase 1 (Nucleus) 6,489,486.00 7 November 1983 6 November 1986 25 July 1986 161 Yorkshire Scarborough
Hemel Hempstead, Phase 1-Main block redevelopment 5,973,576.00 14 November 1983 11 August 1986 27 February 1987 84 3 North West Thames North West Hertfordshire
Clare Hall Project 12,388,823.00 21 November 1983 22 August 1986 30 January 1987 Special Health Authority
Derby Royal Infirmary. Phase 2 9,099,162.00 23 January 1984 19 January 1987 2 October 1986 316 Trent Southern Derbyshire
Harold Wood. Phase 1 8,362,330.00 6 February 1984 6 August 1986 5 January 1987 112 3 North East Thames Barking, Havering and Brentwood
Peterborough 2nd DGH. Phase 1 13,756,438.00 27 February 1984 20 June 1987 11 December 1987 284 4 East Anglian Peterborough
Friarge Hospital, Phase 1 (Nucleus) 5,230,543.00 30 April 1984 31 January 1987 1 September 1986 171 Yorkshire North Allerton
West Dorset DGH. Phase 1 10,681,065.00 30 April 1984 18 November 1986 22 May 1987 134 2 Wessex West Dorset
North Sefton DGH, Southport, Phase 1 (Nucleus) 16,623,819.00 29 May 1984 28 August 1987 31 May 1988 301 4 Mersey North Sefton
St. George's, Block H. Phase 2A 18,004,089.00 4 June 1984 22 November 1987 24 September 1987 360 6 South West Thames Wandsworth
Tameside General, Phase 2 11,464,378.00 16 July 1984 13 March 1987 27 January 1988 139 3 North-Western Tameside
Bournemouth DGH, Phase 1A (Nucleus) 14,636,811.00 6 August 1984 6 May 1987 3 August 1988 289 4 Wessex East Dorset
Telford DGH, Phase 1 (Nucleus) 18,536,334.00 26 November 1984 26 May 1988 31 August 1988 338 4 West Midlands Shropshire
Staincliffe DGH, Phase 1 (Nucleus) 13,467,122.00 7 January 1985 6 July 1988 3 August 1988 306 4 Yorkshire Dewsbury
Walsall, Phase 4A and 4B (Nucleus) 14,679.257.00 7 January 1985 7 July 1988 2 October 1988 297 4 West Midlands Walsall
Bridlington New Community Hospital 11,279,048.00 14 January 1985 11 January 1988 23 October 1987 219 1 Yorkshire East Yorkshire
Oldham DGH, Phase 1 12,819,229.00 11 February 1985 7 February 1988 30 May 1988 307 7 North Western Oldham
City General Stoke, Surgical accommodation (Nucleus) 14,724,874.00 11 March 1985 2 September 1988 4 September 1988 278 West Midlands North Staffordshire
Goole New Community Hospital 9,824,153.00 20 May 1985 16 May 1988 15 January 1988 166 1 Yorkshire Scunthorpe
South Cleveland General, Scheme 2, Phase 1B 6,154,060.00 28 May 1985 28 November 1987 5 February 1988 150 1 Northern South Tees
Cheltenham General, Phase 1B 6,614,327.00 19 August 1985 16 May 1988 1 August 1988 120 2 South-Western Cheltenham
Hammersmith Hospital Redevelopment. Phase 1 12,377,300.00 1 September 1985 1 May 1988 31 March 1988 60 8 Special Health Authority
Chesterfield and NDRH, Phase 2B 6,341,580.00 21 October 1985 10 April 1988 23 November 1987 168 4 Trent North Derbyshire
St. Mary's, Isle of Wight, Phase 3B (Nucleus) 16,986,021.00 28 October 1985 11 September 1988 15 July 1989 187 4 Wessex Isle of Wight
Northern General, Geriatric 6,039,006.00 28 October 1985 26 April 1988 5 February 1988 196 Trent Northern
Broadgreen Development, Phase 1 (Nucleus) 8,903,560.00 6 January 1986 4 January 1988 30 June 1988 292 Mersey Liverpool
Furness General, Scheme 2, Phase 1 6,203,209.00 6 April 1986 21 July 1988 1 October 1988 Northern South Cumbria
Sheffield Children's, Phase 1 Development 5,274,527.00 14 April 1986 6 May 1988 1 October 1988 49 3 Trent Sheffield
Eastbourne New DGH, Phase 2 12,235,727.00 23 June 1986 31 December 1988 31 December 1988 140 South East Thames Eastbourne
Frenchay DGH, Phase 1 6,264,327.00 7 July 1986 3 March 1989 14 July 1989 188 South-Western Frenchay
Mid-Sussex, Phase 1 21,052,954.00 14 July 1986 13 July 1989 30 November 1989 330 4 South West Thames Mid-Downs
Manchester Royal Infirmary, Phase 2 17,723,188.00 14 July 1986 13 January 1990 5 January 1990 280 10 North-Western Central Manchester
Royal Surrey County, Guildford, Phase 2 14,025,105.00 1 September 1986 30 November 1989 30 November 1989 151 South West Thames South-West Surrey
Medway DGH. Phase 3B 13,797,404.00 6 October 1986 31 March 1989 14 June 1989 186 South East Thames Medway
St. Albans—Redevelopment of Main Phase 5,859,553.00 17 November 1986 23 January 1989 31 January 1989 4 North West Thames St. Albans
South Shields General, Scheme 3, Phase 1 12,249,032.00 24 January 1987 25 January 1990 25 January 1990 348 5 Northern South Tyneside
London Hospital (Mile End) 5,440,726.00 2 January 1987 29 April 1989 1 May 1989 144 North East Thames Tower Hamlets
National Heart and Chest Centre, Brompton, Phase 1 17,967,623.00 2 March 1987 23 July 1989 25 July 1989 196 7 Special Health Authority
Glenfield DGH, Phase 2 13,235,906.00 11 May 1987 7 April 1990 25 May 1990 258 4 Trent Leicester
St. Thomas' Hospital—South Wing 9,609,200.00 1 June 1987 31 May 1989 31 May 1989 129 South East Thames West Lambeth
St. Mary's, Portsmouth 7,055,040.00 24 August 1987 22 November 1989 22 November 1989 8 Wessex Portsmouth
Westmoreland DGH, Scheme 1, Phase 1 15,640,127.00 7 September 1987 7 September 1990 7 September 1990 304 2 Northern South Cumbria
Leicester Royal Infirmary, Phase 4B 16,076,376.00 26 October 1987 1 July 1990 1 July 1990 465 Trent Leicester
Whittington Redevelopment, Phase 1 10,932,654.00 2 November 1987 13 August 1990 13 August 1990 244 6 North East Thames Islington
Regional Distribution Centre 7,819,292.00 17 December 1987 13 October 1988 13 October 1988 South East Thames
Royal Victoria Infirmary, Scheme 1, Phase 5 23,268,389.00 4 January 1988 4 July 1991 4 July 1991 360 8 Northern Newcastle
Bognor Community Hospital 5,064,549.00 1 February 1988 30 July 1990 30 July 1990 48 South West Thames Chichester
Odstock Hospital, Salisbury, Phase 1 (Nucleus) 26,564,945.00 22 February 1988 12 July 1991 12 July 1991 212 4 Wessex Salisbury
Milton Keynes DGH, Phase 2 12,664,533.00 11 April 1988 4 June 1990 4 June 1990 168 4 Oxford Milton Keynes
Whipps Cross, Phase 1 11,874,130.00 18 April 1988 19 November 1990 19 November 1990 84 4 North East Thames Waltham Forest