§ Mr. RaffanTo ask the Secretary of State for Wales when he expects the dualling of the A55 expressway across North Wales to be completed; and how much has been spent and is to be spent on the A55, giving the amount for each individual bypass and improvement scheme, together with the dates when they have been or will be completed.
2. Under Construction Scheme Started Estimated completion Estimated gross cost Expenditure to date1 £ million £ million Penmaenbach-Dwygfylchi 1986 1989 24.129 16.646 Conwy Crossing 1986 1991 163.932 59.831 Penmaenmawr bypass 1987 1989 32.251 9.915 Llanfairfechan bypass 1987 1990 20.769 5.216 Northop bypass 1987 1989 11.845 1.400 1 February 1988.
3. Planned Scheme Estimated start Estimated completion Estimated gross cost Expenditure to date1 £ million £ million Travellers Inn improvement 1988–89 1989 3.862 0.283 Pen-y-Clip 1988–89 1991 30.427 2.927 Aber improvement January 1988 to December 19902 — 8.360 0.510 Rhuallt Hill improvement — 8.628 0.498 1 February 1988. 2Roads in Wales timeband.