HC Deb 29 February 1988 vol 128 c439W
Mr. Raffan

To ask the Secretary of State for Wales when he expects the dualling of the A55 expressway across North Wales to be completed; and how much has been spent and is to be spent on the A55, giving the amount for each individual bypass and improvement scheme, together with the dates when they have been or will be completed.

2. Under Construction
Scheme Started Estimated completion Estimated gross cost Expenditure to date1
£ million £ million
Penmaenbach-Dwygfylchi 1986 1989 24.129 16.646
Conwy Crossing 1986 1991 163.932 59.831
Penmaenmawr bypass 1987 1989 32.251 9.915
Llanfairfechan bypass 1987 1990 20.769 5.216
Northop bypass 1987 1989 11.845 1.400
1 February 1988.

3. Planned
Scheme Estimated start Estimated completion Estimated gross cost Expenditure to date1
£ million £ million
Travellers Inn improvement 1988–89 1989 3.862 0.283
Pen-y-Clip 1988–89 1991 30.427 2.927
Aber improvement January 1988 to December 19902 8.360 0.510
Rhuallt Hill improvement 8.628 0.498
1 February 1988.
2Roads in Wales timeband.