HC Deb 30 November 1987 vol 123 cc426-7W
41. Mr. Madel

To ask the Secretary of State for Transport whether any major road repairs are planned on the M1 between where it ends in London and the Bedfordshire/Buckingham border in 1988; and if he will make a statement.

Mr. Peter Bottomley

The following major repairs are planned:

Location Scheme Expected duration
J4–5 Overlay both carriageways and construct climbing lane. Contraflow. March–November
J12–13 Central reserve hardening, adjustment of safety fencing. Lane closures (both carriageways). January–March
J12–13 Overlay northbound carriageway. Contraflow. June–August

All reasonable measures will be taken to reduce delays to the road user, including the use of lane rental contracts.