§ Mr. Campbell-SavoursTo ask the Secretary of State for Defence what is the total cost to date of the battlefield artillery target engagement system to Her Majesty's Government.
310W
§ Mr. SainsburyThe total expenditure to date on all phases of the BATES programme is some £130 million at 1987–88 average outturn prices.
§ Mr. Campbell-SavoursTo ask the Secretary of State for Defence whether the in-service date for the battlefield artillery target engagement system as specified in the battlefield artillery target engagement system original contract is on schedule; and if he will make a statement.
§ Mr. SainsburyI refer the hon. Member to the answer I gave to the hon. Member for Leyton (Mr. Cohen) on 2 November at column605.