HC Deb 10 November 1987 vol 122 c133W
Mr. Barry Jones

To ask the Secretary of State for Wales what is his earliest estimated date for the start and completion of the proposed Deeside community hospital; what is its estimated cost; what are the estimated number of beds; and if he will make a statement.

Mr. Grist

I understand that the current plans of Clwyd health authority, in respect of the proposal to provide a community hospital in Deeside, are to commence construction in September 1989 and to complete it by April 1991, at a total estimated cost of £2.98 million. The development currently envisaged by the health authority makes provision for 28 beds.

The Department is awaiting receipt of a final revised capital programme from Clwyd health authority, which I understand will include the above development.