§ Mr. Corbettasked the Secretary of State for Transport what roadworks are currently being undertaken on the M6 motorway between its junction with the M1 and junction 7; how long they are scheduled to last; what is the cost of each contract and by whom it is being carried out; and what further roadworks are planned for this section of the M6 and at what estimated cost.
§ Mr. Peter BottomleyThe details of the major contracts are:
§ Mr. Corbettasked the Secretary of State for Transport whether he will list the roadworks carried out on the M6 motorway between junctions 5 and 7 since it was opened, giving their duration, cost, purpose and by whom they were completed.
§ Mr. Peter BottomleyDetails of minor repairs could not be listed except at disproportionate cost. The major roadworks contracts have been as follows:
285W
Year and location Type of work Contractor Contract period weeks Cost £ million 1982 Bromford Viaduct, Stage 1 Resurfacing and new joints R. M. Douglas 15 1.1 1983 Bromford Viaduct, Stage 2 Resurfacing and new joints Wrekin Construction 16 1.1 1984 Gravelly Hill Viaduct Resurfacing and new joints R. M. Douglas 12 1.0 Witton Viaduct