HC Deb 13 July 1987 vol 119 cc326-7W
Mr. Janner

asked the Secretary of State for Transport (I) what roadworks are currently being undertaken on the M I motorway between London and Leicester; how long they are expected to last; what further roadworks are planned for this stretch of motorway; whether he will take steps to reduce the delay caused to motorists during the carrying out of such works; and whether he proposes to install any additional motorway lighting on the M 1 between London and Leicester;

(2) what roadworks are currently being undertaken on the M 1 motorway between Leicester and Scotland; how long they are expected to last; what further roadworks are planned on this stretch of motorway; whether he will take steps to reduce the delay caused to motorists during the

Site Scheme Start—Finish dates
J4–5 Resurfacing August 1987–October 1987
J101 Overlay May 1987–October 1987
J12–131 Safety Fence and carriageway renewal October 1987–January 1988
J14–151 Reconstruction/overlay August 1987–January 1988
JI6–171 Central Reserve Reconstruction (Reserve Scheme) February 1988–March 1988
JI91 Construction of Junction for M1–A1 link Spring 1988–Autumn 1988
J23–241 Reconstruction/overlay July 1987–September 1987
J24–R1 Trent Reconstruction/overlay October 1987–November 1987
J231 Reconstruction/overlay February 1988–March 1988
J251 Reconstruction/overlay (Reserve Scheme) February 1988–April 1988
J39–40 Carriageway renewal September 1987–December 1987
1Lane Rental

Further work will take place in future years, with about 5 per cent. of the route renewed each year. Minor repairs and routine maintenance will also take place from time to time. All reasonable measures will be taken to reduce delays to the road user, including the use of lane rental contracts.

Additional lighting is proposed between the end of existing lighting near Newport Pagnell and the Buckinghamshire-Northamptonshire boundary to the north. There are no current proposals for lighting the M1 between Leicester and Leeds.