§ Mr. McNamaraasked the Secretary of State for Defence what has been the cost of United Kingdom air defence ground environment to date.
§ Mr. Archie HamiltonThe cost of the improved UKADGE system has been to date: £348 million (FY 86–87 prices) for the command and control system, new radars and communications. In addition, £44 million (outturn prices) has been spent for associated work services. The contracts for the system are at fixed prices. Some 50 per cent. of the overall cost will be recovered from NATO.
§ Mr. McNamaraasked the Secretary of State for Defence when United Kingdom air defence ground environment will be completed.
§ Mr. Archie HamiltonThe improved UKADGE system will be progressively brought into operation within the next few years. Our priority throughout the transition from the old to the new system will be to ensure that the United Kingdom air defence system will remain fully operational and effective.