HC Deb 06 November 1986 vol 103 cc593-4W
Mr. Ashdown

asked the Secretary of State for Social Services, pursuant to the reply of 29 October, Official Report, column 182, if he is satisfied with the progress and management of studies commissioned to implement recommendations 2 and 3 of the Black report; and when the findings of each study are likely to be received by his Department.

Mrs. Currie

Yes. In studies such as these it is vital that great care be taken to ensure the accuracy of the data collected, even if this results in some delay. According to the latest information received by the Department these studies are expected to be completed by January 1987.

Mr. Ashdown

asked the Secretary of State for Social Services, pursuant to the reply of 29 October, Official Report, column 182, if he has any plans to increase the funding and resources available for the studies commissioned to implement recommendations 1 to 4 of the Black report; and if he will state the total cost and approximate duration of each study.

Mrs. Currie

No. We have no reason to believe additional funding would speed up completion of these studies. The total cost to the Department and approximate duration estimated for these studies are shown in the table; the recommendations 2 and 3 studies are combined as they have been jointly funded.

Total Cost £ Duration (years)
Recommendation 1 57,300 3
Recommendation 2 11,000 2
Recommendation 3 3
Recommendation 4 89,600 3