§ Mr. Spellerasked the Secretary of State for Transport if he will list the anticipated start and completion dates for (a) the north Devon link road stage 2A, (b) the north Devon link road stage 2B, (c) the north Devon link road stage Barnstaple bypass, (d) the A39 Barnstaple relief road, (e) the A39 Bideford bridge completion, (f) the A361 Braunton bypass, (g) the A377 Barnstaple to Exeter improvement and (h) the B3226 Aller Cross to Blackmoor Gate improvement, and any other parts of the north Devon road programme.
§ Mr Michael SpicerThe estimated start and completion dates of trunk road schemes in north Devon which I am at present able to give are:
Start Completion North Devon Link Road Stage 2A Spring 1987 Spring 1989 A39/A361 Barnstaple Bypass Winter 1986/87 Winter 1988–89 A39 Bideford Bypass In progress Summer 1987 Dates for stage 2B of the north Devon Link cannot be determined until the remaining statutory procedures have been completed.
The other road schemes listed are the responsibility of the Devon county council.