§ Mr. Hancockasked the Secretary of State for Defence what is the estimated completion cost of the refurbishment of the wardroom at HMS Nelson Portsmouth; and what was the original estimate.
§ Mr. LeeThe estimated completion cost of the wardroom refurbishment in HMS Nelson is £2.8 million, including VAT. The original 1984 estimate of £2£2 million, exluded VAT and was at the then current price levels.