HC Deb 03 February 1986 vol 91 c61W
Mr. Hancock

asked the Secretary of State for Defence what is the estimated completion cost of the refurbishment of the wardroom at HMS Nelson Portsmouth; and what was the original estimate.

Mr. Lee

The estimated completion cost of the wardroom refurbishment in HMS Nelson is £2.8 million, including VAT. The original 1984 estimate of £2£2 million, exluded VAT and was at the then current price levels.

Forward to