§ Mr. Meadowcroftasked the Secretary of State for Defence what was the average time taken and final price for the last three refits of Oberon class submarines in Rosyth dockyard.
§ Mr. Archie HamiltonOnly two 'O' class refits have so far been completed at Rosyth dockyard. That for HMS Odin cost £26.5 million and took 180 weeks. This included 36 weeks when all resources were transferred to more urgent work arising from the Falklands crisis. HMS Onyx cost £23.895 million and took 127 weeks.