HC Deb 20 November 1985 vol 87 cc190-1W
Mr. Richard Page

asked the Secretary of State for Transport what is his estimate of the current number of vehicles using the stretch of the M25 from Hunton bridge to the M40 interchange per week; and how this figure compares with the figure predicted before that section was constructed.

Mrs. Chalker

The Department's forecasts for traffic flows on this length of M25 were in terms of an annual

Section of M25 16 hour weekday flow
Annual Average Forecast for 1987 (made in 1980) Measured Flow October 1985
M40 Interchange-A412 55,000–60,000 vehicles per day 66,000
A404-Hunton Bridge (A405) 65,000–75,000* 74,000