HC Deb 09 May 1985 vol 78 cc466-7W
Mr. Corbyn

asked the Secretary of State for Transport what has been the average cost of motorway building in rural and urban areas in each year since 1975.

Mrs. Chalker:

Motorway construction costs per mile vary significantly depending on the standard and location of the road concerned. The figures represent very broad average works costs at outturn prices by type of motorway. Additional associated costs such as land acquisition may add between 20 and 25 per cent. to these figures.

£million
Year Rural dual 3-lane Rural dual 2-lane Urban dual 3-lane Urban dual 2-lane
1975 2 1 5 4
1976 2 1 5 4
1977 2 1 5 4
1978 3 2 6 4
1979 3 2 7 5
1980 4 2 9 7
1981 5 3 12 9
1982 5 3 11 8
1983 5 3 12 9
1984* 5 3 12 9
* Provisional.