HC Deb 25 July 1985 vol 83 c653W
Mr. Peter Bruinvels

asked the Secretary of State for Transport if he will now give the expected opening dates of the M25, Reigate to Wisley sections, and all other remaining stages of the M25; and if he will make a statement.

Mrs. Chalker

We expect to have the whole of the M25 open to traffic by the end of 1986. The actual opening dates of the remaining sections will depend on the progress made by individual contractors which in turn is influenced by weather and ground conditions.

The expected opening dates for these unfinished sections are as follows:

Dates
Wisley-Leatherhead August 1985
Leatherhead-Reigate August 1985
Leatherhead Interchange Partly open already but will come into full use August 1985
Poyle-M4 September 1985
M4–M40 September 1985
M4 Interchange June 1986
Swanley-Sevenoaks July 1986
Micklefield Green-Bedmond Road October 1986
Bedmond Road-A405 October 1986
A405-The Bell (A6) November 1986
The Bell-A1 (South Mimms) November 1986