§ Mr. Bruceasked the Secretary of State for Scotland how much is to be spent on the A92 Bridge of Don to the Gordon district/Banff Buchan boundary between 1985 and 1990; and when he expects the major works to be started and completed.
§ Mr. AncramExpenditure on major road improvements for this section of A92-A952 trunk road between 1985 and 1990 is expected to amount to about £10 million. Work on the north Donside road roundabout will commence in the spring of 1986 and will take two to three months to complete. Schemes for Murcar-Balmedie, Tipperty, and Ellon bypass are expected to be ready to start in 1986–87 subject to the satisfactory completion of statutory procedures and the availability of finance. Each of these schemes will require a two-year contract.