HC Deb 22 April 1985 vol 77 cc349-50W
Mr. Peter Bruinvels

asked the Secretary of State for Transport if he will give the most recent estimates of the likely completion dates and any opening dates for the remaining sections of the M25.

Mrs. Chalker

We expect to have the whole of the M25 open to traffic by the end of 1986. The actual opening

Subjects Investigated Date Established Chairman Date Reported
University Education in Dundee 3 May 1951 Baron Tedder April 1952
Scottish Affairs 1952–54 25 July 1952 The Earl of Balfour July 1954
Local Government in Scotland 1966–69 9 June 1966 The Right Hon. Lord Wheatley September 1969
Legal Services in Scotland 25 October 1976 The Right Hon. Lord Hughes CBE May 1980

dates of the remaining sections will depend on the progress made by individual contractors, which in turn is influenced by weather and ground conditions.

The current contract completion dates for the unfinished sections are as follows:—

M4–M40—end July 1985

Wisley-Leatherhead—August 1985

Leatherhead-Reigate—August 1985

Leatherhead Interchange——Complete but opening depends on contracts either side.

Poyle-M4—mid September 1985

M4 Interchange—mid June 1986

Swanley-Sevenoaks—early July 1986

Bedmond Road-A405—Mid September 1986

Micklefield Green-Bedmond Road—early October 1986

The Bell-South Mimms—end October 1986

A405-The Bell (A6)—beginning November 1986