§ Mr. Peter Bruinvelsasked the Secretary of State for Transport when she now expects the Reigate to Leatherhead section of the M25 to be completed; and if he will make a statement.
§ Mrs. ChalkerThe contract completion date is 1 July 1985. The actual completion date will depend on the contractor's progress.