§ Sir Raymond Gowerasked the Secretary of State for Wales if he will give details of progress with new hospital projects and extensions in the Principality.
New hospital projects and extensions in the course of construction, or due to start in 1984 District Scheme Start date Expected completion Total cost (£000's) Clwyd Wrexham DGH Scheme 1 7 September 1981 January 1985 13,211 East Dyfed St. David's, Carmarthen 21 September 1981 September 1984 2,270 Bryntirion Phase II 6 September 1982 September 1985 2,658 Llanelli General Hospital June 1984 November 1987 19,773 Gwynedd Ysbyty Gwynedd 29 March 1976 June 1984 33,543 Llandudno Phase I May 1984 May 1987 1,597 Mid Glamorgan Bridgend DGH 30 June 1980 January 1985 22,450 St. Tydfil's Adaptations 2 March 1984 September 1985 3,302 Powys Ystradgynlais Community Hospital April 1984 May 1986 3,222 South Glamorgan Llandough Obstetric and Associated Works 15 February 1984 1987–88 7,719 Prince of Wales Renovations—all schemes 2,331 Gas Supply March 1984 June 1984 136 Distribution of Gas June 1984 July 1984 50 Boilerhouse April 1984 September 1984 350 Electricity Mains May 1984 September 1984 150 Upgrading of Wards Phase 1 September 1984 June 1985 650 Upgrading of Wards Phase 2 July 1985 April 1986 150 Upgrading of Nurses Accommodation November 1984 June 1985 145 Provision of Modular Operating Theatres September 1985 June 1986 700 West Glamorgan Morriston Nucleus and Upgrading 1 December 1980 March 1985 16,672 Morriston Geriatric Scheme June 1984 March 1986 2,700 Neath OPD 17 November 1982 July 1984 2,090 Singleton Pathology/Mortuary May 1984 May 1986 3,000