§ Mr. Rookerasked the Secretary of State for Transport if he will make a statement giving the latest position regarding the painting of the Gravelly hill interchange, indicating costs and time taken compared with the original estimates.
§ Mrs. ChalkerThe contract was completed in November 1983. The completion date specified in the contract was October 1982. For the other information requested I refer the Hon. Member to my answer to the hon. Member for Birmingham, Erdington (Mr. Corbett) on 23 November 1983 at column 156.