§ Mr. Peter Bruinvelsasked the Secretary of State for Transport what is the anticipated completion date for each of the remaining parts of the M25 currently under construction.
§ Mrs. ChalkerThe estimated completion dates for those sections of the M25 currently under construction are as follows:
223W
Section Estimated Completion Date Heathrow Airport Spur-M4 Summer 1985* M4-M40 Summer 1985 M40-Maple Cross Spring 1985 A10–M11 January 1984 Reigate-Leatherhead Spring 1985 Leatherhead Interchange Spring 1985 Leatherhead-Wisley Autumn 1984 Wisley-Chertsey December 1983 * Completed M4 interchange spring 1986.
§ Mr. Speedasked the Secretary of State for Transport if he will ensure that the M11–A10 section of the M25 motorway is open in time for the Christmas holiday in 1983.
§ Mrs. ChalkerAlthough not programmed for final completion until mid-January, we had hoped to bring this section of M25 into use before Christmas. However, the lighting, ventilation and telecommunication systems, which are essential to the safety of the two tunnels involved, will not be ready by then. The section should be open by the end of January.