HC Deb 19 December 1983 vol 51 c43W
Mr. David Howell

asked the Secretary of State for Energy what is the policy of his Department towards a contract by the British Gas Corporation to purchase (a) some of, and (b) all of the natural gas prospectively available from the Norwegian Sleipner field; and what

Station Estimates Actual/Latest Estimates
Cost £ million (base date prices) Design Capacity MW s.o. Completion date of last operating set Cost £ million (base date prices) Output Capacity MW s.o. Completion date of last operating set
Hinckley Point B* 117 1,240 1973 142 1,040 1978
Dungeness B 111 1,200 1971 269 1,200 1984
Hartlepool 117 1,252 1974 247 1,252 1984
Heysham I 168 1,252 1976 247 1,252 1984
Heysham II 1,251 1,230 1988 1,221 1,230 1988

Note: All cost estimates include initial nuclear fuel.

* Actual figures.

Matters concerning the electricity supply industry in Scotland are the responsibility of my right hon. Friend the Secretary of State for Scotland.