§ Mr. Corbettasked the Secretary of State for Transport whether he will list in the Official Report all current road works on the MI northbound and southbound between junctions 8 and 19; when these are expected to be completed; when they were due to be completed and at what cost against the original estimate.
§ Mrs. ChalkerThe information requested is as follows:
when these are expected to be completed; when they were due to be completed; and at what cost against the original estimate.
§ Mrs. ChalkerThe information requested is as follows: 627W
M6 Location Works in Progress Programmed Completion Date Expected Completion Original Estimated Cost Current Estimated Cost Junctions 5–6 Renewal of bearing plinths on Bromford Viaduct March 1984 March 1984 £510,000 £510,000 5–6 Repairs to hard shoulder verge on northbound carriageway December 1983 December 1983 £5,000 £5,000 6–7 Repairs to parapst rail on southbound carriageway December 1983 December 1983 £6,000 £6,000