§ Mr. Barry Jonesasked the Secretary of State for Wales what is his estimate of the total cost and completion date for the Bangor district hospital, Mold community hospital and Wrexham district hospital; and if he will make a statement.
§ Mr. Wyn Roberts:The information requested is as follows:
418W
Scheme Latest estimated total cost £ million Expected contract completion date Ysbyty Gwynedd (Bangor DGH) 25.508 16 November 1982 Mold community hospital 1.774 17 February 1984 Wrexham DGH 12.968 7 January 1985 At Bangor, the following contracts are yet to be completed—
Contract Latest estimated cost £ million Expected contract completion date Additional works 1.339 March 1983 Residential accommodation 0.266 July 1983 Catering department 1.088 May 1984