HC Deb 27 October 1982 vol 29 cc455-6W
Sir David Price

asked the Secretary of State for Transport if he will list in the Official Reportall the bypass schemes which he has authorised in the last 12 months, giving the estimated cost and the completion date in each case.

Mrs. Chalker:

I have authorised the start or resumption of preparation work on the trunk road bypass schemes attached since 27 October 1981. At this early stage it is not usually possible to give any estimate of cost, which will depend to a large extent on the route and nature of the preferred scheme, nor of any precise timing.

In addition I have provided funds in the transport supplementary grant settlement for 1982–83, so that county councils may plan to start a further 35 bypasses on local roads.

SCHEME:

A41 Bicester Southern bypass

A259 Winchelsea bypass

A6 Quorn & Mountsorrel bypass

A36 Beckington bypass

A249 Iwade bypass

A43 Blisworth bypass*

A595 Egremont by pass

A596 Wigton bypass

A4/A46 Batheaston & Swainswick bypass*

A6 Burton Latimer & Rushden bypass*

A6(M) Stockport & Hazel Grove bypass*

A35 Axminster bypass*

A46 Newark relief road*

A59 Burscough by pass*

A27 Pevensey bypass*

A3 Milford bypass*

A6 Barton (Bedfordshire) bypass*

A16 Spalding & Sutterton bypass*

A27 Westhampnett diversion*

A35 Charmouth by pass*

A41 Whitchurch (Shropshire) bypass*

A140 Scole bypass

A303 Sparkford bypass*

A420 Kingston Bagpuize & Southmoor bypass

A428 Levendon bypass

A435 Norton & Lenchwick bypass*

A516 Etwall bypass*

A696 Woolsington & Kenton Bank Foot bypass*

Schemes marked*have been revived in part or whole from the list of suspended schemes.