HC Deb 19 May 1982 vol 24 c130W
Sir David Price

asked the Secretary of State for Transport what progress has been made with the construction of the missing section of the M27 between the parishes of Hedge End and Chilworth; and when he expects this section to be open to traffic.

Mrs. Chalker

A contract for construction of part of this section was let at the end of last year. The remaining contract was let on 17 May.

I expect the whole section to be completed and in use by the autumn of 1984.