HC Deb 19 July 1982 vol 28 c75W
Mr. Norman Hogg

asked the Secretary of State for Scotland what is his estimate of Scotland's electricity generating capacity and demand once Torness nuclear power station is commissioned.

Mr. Alexander Fletcher

The forecasting of electricity demand is the responsibility in the first instance of the Scottish electricity boards. I understand from recent load forecasts that by the early 1990s the boards estimate that the all-Scotland demand will be approaching 7,000MW. At that time the operational capacity is expected to be of the order of 10,000MW, excluding plant in store.