§ 29. Mr. Brocklebank-Fowlerasked the Secretary of State for Transport when he expects construction work on the A17 Clenchwarton/Terrington St. Clement/Walpole Cross Keys bypass to be completed; and if he will make a statement.
§ Mrs. ChalkerIn May; but at the present good rate of progress it should be open to traffic by the end of the year, except for a short stretch at the western end where there will be a diversion while the connection with the existing road is completed.