HC Deb 10 February 1982 vol 17 cc407-8W
Mr. Spearing

asked the Secretary of State for the Environment if he will set out in the Official Report a timetable of expected completions of private dwellings on each of the housing projects arranged by the London Dockland Development Corporation.

Mr. Giles Shaw

The first phase of housing development in Beckton, on the Cyprus 3 site, is now under construction. Some 610 units, most for owner-occupation, are expected to be completed within the next two years. I understand that proposals are being considered from some 470 units in the Surrey docks area, on which development is expected to start in April and to be completed within 2 years. Other sites in Newham, Tower Hamlets and Southwark are expected to be developed for housing later in the year but completion dates have not been fixed.